Listen Live

John Hart decommissioning project nearly finished

The decommissioning of the John Hart Generating Station is in its final stages.

Built in 1947, the station needed to be replaced.

The existing facility and pipelines were unlikely to withstand even a moderate earthquake.

BC Hydro spokesperson Stephen Watson said the new underground John Hart powerhouse going into service last fall has enabled BC Hydro to remove the old above-ground facility.

He added that the new facility is designed to be seismically strong, reliable, and protects downstream fish habitat from unplanned river flow reductions from the powerhouse.

“Being underground, it is in rock (that is) seismically strong, we have a new powerhouse, and we have a water bypass facility within the powerhouse to maintain fish flows.”

Milestones since June 30 include: 

  • The wooden penstocks have been completely removed, along with the removal of contaminated soils from the corridor;
  • The original generating station has been demolished with the site flattened and prepared for new lookout site;
  • Two of the three surge towers were felled, then cut up and removed for steel recycling;
  • The surge tower site has been remediated, with office trailers removed, site levelled and prepared for revegetation;

A new trail has been designed and construction is underway to reconnect Canyon View Trail loop; and there have been new public river put-in improvements – with a rock pad design and installation for kayaks, canoes and river rafts only.

The next steps from October to November include: 

  • Laydown areas demobilized and remediated;
  • Planting throughout the construction corridor;
  • Canyon View Trail loop will be reinstated by the river, including the viewing area at the old generating station site; and
  • the final clean up at the old Campbellton School site.

A total of 95 percent of the lower Campbell River comes out of the John Hart Generating Station. A new water bypass will ensure that if we need to shut down the facility for any reason, water flow can be maintained for fish and fish habitat.

Watson said crews are nearing the finish line.

“The past nine months have been working away to remove that old above-ground hydroelectric facility, and the planting has started to allow the penstock corridor and other laydown areas to essentially become forest again, so we’re at the very end of this overall project that basically started with site preparation way back in 2013.” 

Just over $1 billion was budgeted for the project and Watson said it is “on budget.”

Watson noted that as many as 500 people worked on the project in 2017, with over more than 100 service contractors and suppliers.

Continue Reading

cfcp Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Infrastructure, housing, UNDRIP will top agenda as local governments meet in Victoria next week

Members of local governments and First Nations are gathering in Victoria next week for the annual Union of B.C. Municipalities (UBCM) convention.

Fundraiser walk supporting Comox Valley seniors set for Sunday

The Glacier View Lodge Society is welcoming walkers to support its 2025 Walk for Glacier View, individual walkers or teams will take a scenic 2km walk around the lodge while taking in a bake sale, live music and other entertainment.

NCI officially opens new student housing buildings

A student housing project at Courtenay's North Island College has officially opened its doors.

B.C. Conservatives support federal bill to classify intimate partner killings as first-degree murder

B.C. politicians are voicing support for a federal Conservative bill that would classify the killing of an intimate partner as first-degree murder. 

“Please stop”: Eby says Alberta’s pipeline dream jeopardizes B.C. projects

Premier David Eby said Alberta’s push for a new pipeline is a threat to existing major projects in B.C. 
- Advertisement -